News Release
U.S. Environmental Protection Agency
New England Regional Office
April 19, 2012
U.S. Environmental Protection Agency
New England Regional Office
April 19, 2012
Contacts: EPA Public Affairs, (617) 918-1010
Final Clean Water Permit Issued for Proposed Russell Biomass Facility in Russell, Mass.
The facility is proposed to be built adjacent to the Westfield River, and to withdraw water from and discharge water back into the Westfield River. The final permit contains stringent protections including limiting the facility’s discharge of heat and other effluents to the water, and monitoring requirements to ensure the protection of aquatic organisms and habitat quality in the river.
The permit also ensures that the entrainment and impingement of fish and other river organisms is minimized with the requirement to use closed cycle cooling towers, which was determined to be the best technology available for controlling the adverse effects of cooling water withdrawal at Russell Biomass.
The permit was first proposed in 2009 and underwent a formal public review and comment period. Following EPA’s careful review of comments submitted on the proposal, EPA revised and strengthened various protections for the river, including: imposing monthly monitoring of aluminum levels; added an “average monthly rise” phosphorus limit, which allows no detectable difference between the intake and discharge mass of phosphorus; and quarterly turbidity monitoring requirements for the stormwater outfall locations as well as a location upstream.
The permit becomes effective on July 1, 2012. If information becomes available to EPA which indicates that new or more stringent permit limits are needed to meet water quality standards, the permit may be modified.
More information: The final Russell Biomass plant NPDES permit and other documents (http://www.epa.gov/region1/npdes/permits/2012/finalma0040371permit.pdf
# # #