Third and Most
Successful Season of Hudson River Dredging Ends Today
More Than 1.3 Million Cubic Yards of
PCB-Contaminated Sediment
Removed Since 2009
Dredging Start
Contact:
Mary Mears, 212-637-3673, mears.mary@epa.gov
(Fort
Edward, NY – November 13, 2012) The U.S. Environmental Protection Agency today
announced that as the third season of dredging draws to a close later this week,
a total of more than 1.3 million cubic yards of sediment contaminated with PCBs
will have been removed from the Hudson River. Since dredging began on May 9,
2012, about 650,000 cubic yards of sediment were dredged from a three-mile
section of the river south of the village of Fort Edward, New York, exceeding
the season goal of dredging 350,000 cubic yards. With the third season of
dredging nearly complete, the EPA is almost half way toward its goal of removing
2.65 million cubic yards of contaminated sediment from a 40-mile stretch of the
upper Hudson River. The dredging project also created 500 jobs and additional
economic benefits for the area.
All
of the EPA-required limits on the amount of sediment stirred up and resuspended
during the dredging and the amount of area that can be capped were met. Over the
next several weeks, clean material will be placed over the areas that were
dredged.
“With
the third season of dredging nearly complete, the EPA is approximately half way
toward its goal of a cleaner Hudson River,” said Judith A. Enck, EPA Regional
Administrator. “With each successful dredging season, we draw closer to a
healthier Hudson River and to the day when we can restore this historic river to
its former glory.”
PCBs
are likely cancer-causing chemicals and can cause neurological damage,
especially in children. They build up in the fatty tissue of fish and other
animals. The primary health risk to people is from eating contaminated fish.
Over
a 30-year period, ending in the late 1970’s, an estimated 1.3 million pounds of
PCBs entered the river from two General Electric capacitor manufacturing plants
located in Fort Edward and Hudson Falls, New York. The EPA is overseeing the
dredging project that is being conducted by General Electric under the terms of
a 2006 legal agreement.
During
dredging, the EPA required extensive monitoring to ensure that the amount of
sediment drifting downriver during the operation was within acceptable limits.
The EPA
also set a requirement that no more than two percent of the total amount of PCBs
actually removed from the river could be stirred up and resuspended in the
water, as measured at Schuylerville, which was the monitoring station nearest to
where dredging occurred in 2012. The requirement for Waterford, the farthest
downstream monitoring station in the upper Hudson River, was no more than one
percent of the amount removed. Both of these requirements were met during the
2012 dredging season. The requirement that capping not exceed 11% of the total
project area was met with less than 5% of the area being capped, not counting
those areas where capping is unavoidable, was also met.
The
EPA also required monitoring to gauge impacts on surrounding communities, such
as noise and air quality. Operational changes, which included keeping dredged
sediment in barges covered with water and prioritizing the transport and
processing of the most contaminated sediment first, reduced air quality and
noise impacts during the 2012 season.
In
the coming months the EPA will determine what changes, if any, are needed for
the next season of dredging set to begin next spring. The shipment of dredged
sediment to permitted out-of-state disposal facilities will continue this
calendar year until all dredged sediment remaining at the Fort Edward processing
facility has been transported off-site by train.
During
the initial years of the project, the areas targeted for dredging were close
together and generally extended from shoreline to shoreline. In future years, as
the project continues to move southward towards Troy, the dredging areas will be
further apart. Several areas will also need to dredged that are logistically
challenging, including those near dams, shallow areas behind islands and the
landlocked section of river located between the Thompson Island Dam and Fort
Miller Dam. The rest of the cleanup is expected to take three to five more years
to complete.
For more information about the Hudson River
dredging project, visit http://www.epa.gov/hudson
and http://www.hudsondredgingdata.com.
12-
138 #
# #
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.